Estimating, Cost Planning, Quantity Surveying
Heritage building remediation including relocation, environmental mitigation and infrastructure upgrade.
Partial demolition of the Victorian Ledger Building at London City Airport, the relocation of staff to new accommodation in the western car park, the construction of a new sound screen, and the erection of a new permanent airside fence.
Quant Measur provided initial budget estimates and full cost plan management through design development, and site administration throughout construction, agreeing interim payment valuations and producing monthly cost assessments for the client.
Heritage building remediation
Estimating, Cost Planning, Quantity Surveying
Sound screen and airside fence
Key responsibilities across the project.
Provided initial budget estimate and management of same during design development.
Provided a final detailed cost plan and advice on the project budget.
Attended site meetings, agreed interim payment valuations and provided monthly cost assessments.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 14, 2026
Home 5 Project Tag: Estimating ( Page 6 )
Terminal Check-in Desk & Baggage Belt Replacement
Estimating, Cost Planning, Quantity Surveying
Operational modification enhancing check-in efficiency and passenger processing capacity.
Modification of check-in desks at London City Airport including the removal and repositioning of check-in desks, repositioning of FIDS, the supply and installation of new weigh and dispatch conveyors, the reconfiguration of associated services, and all associated builders work.
Quant Measur provided site administration throughout, attending site meetings, agreeing interim payment valuations with the Contractor and producing written monthly cost assessments for the client.
Check-in desk and baggage belt
Estimating, Cost Planning, Quantity Surveying
FIDS repositioning, new conveyors
Key responsibilities across the project.
Attended site meetings, agreed interim payment valuations with the Contractor and issued corresponding certificates.
Assisted in the preparation of written monthly assessments of progress and anticipated final cost for the client.
Removal and repositioning of check-in desks, repositioning of FIDS, supply and installation of new weigh and dispatch conveyors, reconfiguration of associated services and all associated builders work.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 14, 2026
Home 5 Project Tag: Estimating ( Page 6 )
City Aviation House Canteen
Estimating, Cost Planning, Quantity Surveying
Staff facility development improving airport operational team welfare provision.
Strip-out of existing office accommodation from City Aviation House and provision of a new staff canteen, including the upgrade and reconfiguration of Mechanical and Electrical plant to suit the new layout.
Quant Measur provided site administration throughout, attending site meetings, agreeing interim payment valuations with the Contractor and producing written monthly cost assessments for the client.
Staff canteen fit-out and M&E upgrade, City Aviation House
Estimating, Cost Planning, Quantity Surveying
Key responsibilities across the project.
Attended site meetings, agreed interim payment valuations with the Contractor and issued corresponding certificates.
Assisted in the preparation of written monthly assessments of progress and anticipated final cost for the client.
Strip-out of existing office accommodation, provision of new staff canteen, full upgrade and reconfiguration of M&E plant to suit new layout, testing and commissioning.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 14, 2026
Home 5 Project Tag: Estimating ( Page 6 )
Estimating, Cost Planning, Quantity Surveying
Office accommodation development supporting expanded administrative operations.
Strip-out of existing ground floor kitchen preparation and storage areas from King George V House and provision of new office accommodation, inclusive of raised floor, kitchenette and toilet facilities, and the upgrade and reconfiguration of Mechanical and Electrical plant to suit the new layout.
Quant Measur provided site administration throughout, attending site meetings, agreeing interim payment valuations with the Contractor and producing written monthly cost assessments for the client.
Ground floor office fit-out
Estimating, Cost Planning, Quantity Surveying
Raised floor, kitchenette, M&E
Key responsibilities across the project.
Attended site meetings, agreed interim payment valuations with the Contractor and issued corresponding certificates.
Assisted in the preparation of written monthly assessments of progress and anticipated final cost for the client.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 14, 2026
Home 5 Project Tag: Estimating ( Page 6 )
Terminal Concourse Toilet Refurbishment
Estimating, Cost Planning, Project Management
Enhanced passenger facilities across landside airport terminal concourse areas.
Refurbishment of the existing landside WC, Disabled and First Aid facilities (known collectively as the Concourse Toilets) at London City Airport. The project included provision of temporary facilities in the Triangle to maintain passenger access throughout the refurbishment works.
Quant Measur provided full cost management from initial budget estimate through to final cost plan, managed the tender process including advising on form of contract, preparing Preliminaries and administering the tender, and provided site administration throughout delivery.
Landside WC, Disabled and First Aid
Estimating, Cost Planning, Project Management
Temporary facilities maintained
Key responsibilities across the project.
Provided initial budget estimate and management of same during design development.
Advised on form of contract, prepared Preliminaries and administered the tender process.
Provided a final detailed cost plan and advice on the project budget.
Attended site meetings, agreed interim payment valuations and provided monthly cost assessments.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$