Containment Boom Replacement — Pollution Control
Estimating, Cost Planning, Contract Administration
Commercial support for a preventative marine pollution intervention.
The provision of a full chain replacement for a length of containment boom, replacement of anchor chains and removal of existing rope connections, and replacement of the pollution skirt. The works were preventative — designed to maintain the boom's ability to contain potential pollution in the event of a marine incident.
We were appointed to provide commercial support across the full lifecycle of the project. Our role focused on giving the client cost confidence on a preventative environmental intervention with clear regulatory and reputational stakes.
UK Ports & Harbours Operator
Estimating, Cost Planning, Contract Administration
Specialist services contract
Key responsibilities across the project.
Producing an initial budget estimate covering chain replacement, anchor chains, and the pollution skirt — providing the client with a clear cost build-up to support investment approval.
Preparing a final detailed cost plan and advising on the overall project budget.
Attending site and progress meetings as required, agreeing interim payments with the contractor in line with the contract, and issuing the corresponding certificates.
Preparing written monthly assessments of progress, including anticipated final cost of the works.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 21, 2026
Home 5 Project Tag: Estimating ( Page 5 )
Topography & Drainage Survey
Estimating, Cost Planning, Contract Administration
Cost-controlled survey commission supporting asset data.
The provision and update of topographical information to support asset records, alongside a survey of the foul and surface water drainage system. The works supported the client's asset information base — providing the up-to-date evidence needed to inform downstream maintenance, capital planning, and regulatory reporting.
We were appointed to provide commercial support across the survey commission — from establishing the cost case through to final account. Our role focused on ensuring a survey-led project was procured and delivered within a clear and defensible commercial framework.
Estimating, Cost Planning, Contract Administration
Specialist services contract
Key responsibilities across the project.
Producing an initial budget estimate covering both the topographical and drainage survey scopes, providing a clear cost build-up to support investment approval.
Preparing a final detailed cost plan and advising on the overall project budget as the precise survey extents were confirmed.
Attending progress meetings as required, agreeing interim payments with the survey contractor in line with the contract, and issuing the corresponding certificates.
Preparing written monthly assessments of progress, including anticipated final cost, supporting client reporting on asset-information spend.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 15, 2026
Home 5 Project Tag: Estimating ( Page 5 )
Cost Management, Contract Administration
Ongoing management of fuel facility infrastructure to maintain safe operation.
The provision of services to maintain the safe operation of the fuel facility — helping to maintain the condition of the fuel facility infrastructure throughout its life and ensuring the facility is functioning correctly. The work was delivered through the management of various specialist contractors and consultants engaged in planning, costing and reviewing technical information for the works to be carried out in a cost effective and timely manner.
Quant Measur supported the Client through ongoing site administration, attending progress meetings, agreeing interim payment valuations with contractors and issuing the corresponding certificates. Monthly assessments of progress and anticipated final cost were prepared throughout the engagement to keep the Client fully appraised.
Cost Management, Contract Administration, QS
Ongoing facility management
Coordination of multiple specialist contractors
Key responsibilities across the project.
Attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates.
Assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 14, 2026
Home 5 Project Tag: Estimating ( Page 5 ) Estimating, Cost Planning, Quantity Surveying
Specialist marine engineering reducing electromagnetic interference from subsea infrastructure.
Specialist marine engineering works to remove steel casings from concrete piles beneath Hold 28 at London City Airport, in order to reduce the magnetic field generated by the subsea infrastructure and minimise electromagnetic interference affecting aircraft operations.
Quant Measur provided site administration throughout, attending site meetings, agreeing interim payment valuations with the Contractor and producing written monthly cost assessments for the client.
Specialist marine engineering
Estimating, Cost Planning, Quantity Surveying
Key responsibilities across the project.
Attended site meetings, agreed interim payment valuations with the Contractor and issued corresponding certificates.
Assisted in the preparation of written monthly assessments of progress and anticipated final cost for the client.
Specialist marine engineering works to remove steel casings from concrete piles beneath Hold 28, reduction of magnetic anomaly field, reinstatement and verification works.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS
by char@hecreative.com | May 14, 2026
Home 5 Project Tag: Estimating ( Page 5 )
Stand 1–21 Apron Strengthening
Estimating, Cost Planning, Quantity Surveying
Specialist pavement strengthening enabling continued aircraft stand operations.
Strengthening of the apron pavement between Stands 1 to 21 at London City Airport, through hydro demolition, provision of additional steel reinforcement and concrete, and installation of expansion joints.
Quant Measur provided site administration throughout, attending site meetings, agreeing interim payment valuations with the Contractor and producing written monthly cost assessments for the client.
Estimating, Cost Planning, Quantity Surveying
Hydro demolition and reinforcement
Key responsibilities across the project.
Attended site meetings, agreed interim payment valuations with the Contractor and issued corresponding certificates.
Assisted in the preparation of written monthly assessments of progress and anticipated final cost for the client.
Hydro demolition of existing apron pavement, provision of additional steel reinforcement and concrete, installation of expansion joints, reinstatement of apron surface across Stands 1–21.
Related projects we have delivered.
Let's discuss
your project.
We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.
$
20 Tadworth Parade, Elm Park, Essex, RM12 5AS