Stand 1–21 Apron Strengthening

Estimating, Cost Planning, Quantity Surveying

$

Project overview

Specialist pavement strengthening enabling continued aircraft stand operations.

Strengthening of the apron pavement between Stands 1 to 21 at London City Airport, through hydro demolition, provision of additional steel reinforcement and concrete, and installation of expansion joints.

Quant Measur provided site administration throughout, attending site meetings, agreeing interim payment valuations with the Contractor and producing written monthly cost assessments for the client.

$

Project stats

Client

London City Airport

Sector

Transport

Stands

1–21

Services delivered

Estimating, Cost Planning, Quantity Surveying

Method

Hydro demolition and reinforcement

$

Our role

Key responsibilities across the project.

Site Administration

Attended site meetings, agreed interim payment valuations with the Contractor and issued corresponding certificates.

Cost Reporting

Assisted in the preparation of written monthly assessments of progress and anticipated final cost for the client.

Scope of Works

Hydro demolition of existing apron pavement, provision of additional steel reinforcement and concrete, installation of expansion joints, reinstatement of apron surface across Stands 1–21.

$