Project overview

Full cost development on a major terminal optimisation scheme.

The reconfiguration and refurbishment of the main terminal building, undertaken as a major operational optimisation scheme.

We were appointed to provide commercial support across the full pre-contract phase. Our role spanned initial budget estimating, detailed cost planning through design development, and the production of a final detailed cost plan — providing the client with the cost evidence to support a major capital investment.

$

Project stats

Client

UK Airport Operator

Sector

Transport

Services delivered

Estimating, Cost Planning

Contract Type

Pre-contract advisory

$

Our role

Key responsibilities across the project.

Initial Budget Estimate

Producing an initial budget estimate to inform the client's business case for the terminal optimisation scheme.

Detailed Cost Plan

Preparing a detailed cost plan and managing it through the design development stage — providing the client with a continuously refined cost picture.

Design Development Review

Reviewing the cost position during design development and updating the cost plan as the terminal reconfiguration and refurbishment was refined.

Final Cost Plan & Budget Advice

Preparing a final detailed cost plan and advising on the overall project budget — providing the cost evidence base for a major capital investment decision.

$

Get in Touch

Let's discuss
your project.

We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.

$

London Office

20 Tadworth Parade, Elm Park, Essex, RM12 5AS

Gates 3–8 Over Lounge & Eastern Apron Gate — Concept Estimate

Gates 3–8 Over Lounge & Eastern Apron Gate — Concept Estimate

Home 5 Project Tag: Estimating ( Page 2 )
$

Transport

Gates 3–8 Over Lounge & Eastern Apron Gate — Concept Estimate

Estimating, Cost Planning

$

Project overview

Concept-stage cost development supporting a business case.

Development of a concept estimate to support the client's business case process for a Gates 3–8 over-lounge facility and an Eastern Apron gate — strategic cost evidence for a passenger infrastructure scheme.

We were appointed to provide commercial support across the concept and design development phases. Our role focused on cost planning that gave the client the evidence base needed for business case decision-making.

$

Project stats

Client

UK Airport Operator

Sector

Transport

Services delivered

Estimating, Cost Planning

Contract Type

Pre-contract advisory

$

Our role

Key responsibilities across the project.

Detailed Cost Plan

Producing a detailed cost plan and managing it through the design development stage, providing the client with a continuously refined cost picture.

Design Development Review

Reviewing the cost position during design development and updating cost plans as the over-lounge and Apron gate concept was refined.

Final Cost Plan & Budget Advice

Preparing a final detailed cost plan and advising on the project budget — providing the cost evidence base for the client's business case decision.

$

Get in Touch

Let's discuss
your project.

We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.

$

London Office

20 Tadworth Parade, Elm Park, Essex, RM12 5AS

Bastion Mike Ramp — Rotary Wing Ramp Construction

Bastion Mike Ramp — Rotary Wing Ramp Construction

Home 5 Project Tag: Estimating ( Page 2 )
$

Defence

Bastion Mike Ramp — Rotary Wing Ramp Construction

Estimating, Cost Planning, Risk Management

$

Project overview

Cost development on a major Defence rotary wing facility.

The construction of a 170,000m² rotary wing ramp, complete with associated infrastructure and associated buildings, alongside the production of a 3-point estimate to support project decision-making at Camp Bastion.

We were appointed to provide commercial support at the budget stage. Our role focused on producing an initial budget estimate, a 3-point estimate to capture cost risk, and advising on the overall project budget for a major Defence infrastructure scheme.

$

Project stats

Client

UK Defence Sector

Sector

Defence

Services delivered

Estimating, Cost Planning, Risk Management

Contract Type

Defence sector pre-contract advisory

$

Our role

Key responsibilities across the project.

Initial Budget Estimate

Producing an initial budget estimate covering the 170,000m² rotary wing ramp and its associated infrastructure and buildings — providing a clear cost build-up.

3-Point Estimating

Producing a 3-point estimate to capture the cost risk profile of a major Defence facility delivered into a Theatre environment.

Budget Advice

Advising on the overall project budget, supporting Defence decision-making on a strategically significant facility.

$

Get in Touch

Let's discuss
your project.

We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.

$

London Office

20 Tadworth Parade, Elm Park, Essex, RM12 5AS

Defence Estates — Various Contracts & Estimating Tools

Defence Estates — Various Contracts & Estimating Tools

Home 5 Project Tag: Estimating ( Page 2 )
$

Defence

Defence Estates — Various Contracts & Estimating Tools

Contract Strategy, Estimating, Risk Management

$

Project overview

Estimating frameworks for Theatre Defence operations.

The provision of various contract documentation for projects in the Middle East — engaging contractors for planned and reactive maintenance works. Alongside this, the production of a costing database to assist in the production of Project Rough Order of Costs, modifications to the Risk Register and 3-point estimating template (with guideline documentation) to assist with identifying the semi-quantitative value of risk within Theatre projects, and the manufacture of a whole life cost and construction feasibility template for the comparison of various building levels within Theatre — supporting project business cases.

We were appointed to provide commercial and contractual support across multiple Defence estate engagements. Our role focused on building the documentation and estimating tools needed to deliver consistent commercial control across Theatre operations.

$

Project stats

Client

UK Defence Sector — Theatre Operations

Sector

Defence

Services delivered

Contract Strategy, Estimating, Risk Management

Contract Type

Multi-contract Defence arrangement

$

Our role

Key responsibilities across the project.

Contract Documentation

Producing various contract documentation to support the engagement of contractors for planned and reactive maintenance works on Defence estate projects in the Middle East.

Costing Database Development

Producing a costing database to assist in the production of Project Rough Order of Costs, providing a structured estimating foundation for Theatre projects.

Risk Register & 3-Point Estimating

Modifying the Risk Register and 3-point estimating template, complete with guideline documentation, to assist with identifying the semi-quantitative value of risk within Theatre projects.

Whole Life Cost Template

Manufacturing a whole life cost and construction feasibility template for the comparison of various building levels within Theatre — supporting project business cases.

$

Get in Touch

Let's discuss
your project.

We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.

$

London Office

20 Tadworth Parade, Elm Park, Essex, RM12 5AS

Wash Areas — Hire Car Facility Extension

Wash Areas — Hire Car Facility Extension

Home 5 Project Tag: Estimating ( Page 2 )
$

Commercial & Institutional

Wash Areas — Hire Car Facility Extension

Estimating

$

Project overview

Early-stage budget support for a hire car facility extension.

The provision of an additional operations building facility and additional wash areas for a hire car facility — an extension of operational infrastructure supporting hire car services.

We were appointed to provide commercial support at the early budget stage. Our role focused on producing an initial budget estimate and advising on the overall project budget, providing the client with the cost evidence to assess the case for the extension.

$

Project stats

Client

UK Site Operator

Sector

Commercial & Institutional

Services delivered

Estimating

Contract Type

Pre-contract advisory

$

Our role

Key responsibilities across the project.

Initial Budget Estimate

Producing an initial budget estimate covering the operations building and additional wash areas — providing the client with a clear, defensible cost build-up.

Budget Advice

Advising on the overall project budget, providing the client with the evidence to assess the commercial case for the extension.

Investment Decision Support

Supporting the client's early-stage investment decision-making with proportionate, focused commercial input.

$

Get in Touch

Let's discuss
your project.

We'd love to hear about your requirements. Get in touch and one of our team will be in contact shortly.

$

London Office

20 Tadworth Parade, Elm Park, Essex, RM12 5AS