Case Studies

Aviation

VCP Dot Matrix Sign

The provision of Vehicle Check Point Dot Matrix Sign and associated Infrastructure to provide information at a vehicle check point.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.

FEGP

The delivery of 2 FEGP stands in order to meet our S106 obligation within a dry dock further to complex discussions with authorities to mitigate environmental risk and align to a dock lowering schedule.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Installation of new Winsock Poles c/w new LED lights

Move two masts away from the dock edge so essential maintenance can be achieved safely, provide new masts and associated infrastructure including LED fittings.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Noise Monitoring Terminal

The provision of Noise Monitoring Terminals and associated infrastructure works at two separate locations.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur assisted with the issue of form of contract to be utilised, and the proposed amendments to contract conditions, preparation of the Preliminaries document, the administration of the tender process and act on behalf of the Client in liaising with Contractors as necessary, and provided recommendations on the contract price.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Pavement Classification Survey

Provision of survey works to determine bearing strength for types of aircraft expected to use aerodrome. Works included UO Survey, GPR Survey, DCP, coring and HWD testing.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Resealing of runway and Apron concrete joints

Resealing of bay joints. To control FOD and prolong pavement life.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

PQC Bay replacement Project

The replacement of 48 cracked bays identified, where crack repairs is no longer effective in maintaining integrity of bays to control FOD risk and pavement structure.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Bulk Lamp Change

The provision of regulatory bulk lamp change of AGL fittings.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Runway Survey condition Project

The friction Test of Runway and remedial works further to findings.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated final cost of the works.

Replacement of DC Control Wiring

The provision of DC control wiring and switching units.
Quant and Measur provided an initial budget estimate and management of the same during the design development and a final detailed cost plan and advise on the project budget.
Quant and Measur assisted with the issue of form of contract to be utilised, and the proposed amendments to contract conditions, preparation of the Preliminaries document, the administration of the tender process and act on behalf of the Client in liaising with Contractors as necessary, and provided recommendations on the contract price.
Quant and Measur attended site / progress meetings as required, agreed with the Contractor the value of interim payments in accordance with the contract and notified the Client and Contractor accordingly by issue of the corresponding certificates, assisted in the preparation of written monthly assessments of the progress of the works for consideration by the Client, including the anticipated